How long does it take to open a restaurant in Los Angeles?

Design, permits and construction, step by step

Most first-time owners plan for construction and forget the months before it. In Los Angeles the time between signing a lease and the first day of construction is often as long as construction itself.

The usual order

For a typical tenant improvement, owners should expect roughly two to four months for design and drawings, two to six months for permits, and three to six months for construction. A full project commonly takes eight to fourteen months. A simple refresh of an existing restaurant can be much faster.

Building permits

In the City of Los Angeles, plans go to the Department of Building and Safety. Burbank, Glendale, Pasadena, Beverly Hills, West Hollywood and Santa Monica have their own building departments and their own timing. Plan check returns corrections, the design team answers them, and this repeats until the plans are approved. The City of Los Angeles also runs a Restaurant and Hospitality Express Program that assigns a case manager to help food businesses through the departments.

Health department review

Food facilities need plan approval from the health department before construction starts. In most of the county that is the Los Angeles County Department of Public Health; Pasadena, Long Beach and Vernon have their own. Submit health plans at the same time as building plans, not after.

Alcohol

Alcohol takes two approvals: a state license from the California Department of Alcoholic Beverage Control and a local land-use approval. In the City of Los Angeles that is either a Conditional Use Permit or, for qualifying sit-down restaurants, the faster Restaurant Beverage Program. Start both as early as possible, because a full conditional use process can outlast the whole build-out.

What slows projects down

The fastest projects are the ones where the concept, the kitchen equipment and the seat count are decided before the drawings begin.

Sources

By Albert Galstyan · November 11, 2026

Related projects

Images are visualizations unless stated otherwise.

Questions

Can I start construction while permits are in review?

No. Work that needs a permit must wait for the permit. Ordering long-lead items such as kitchen equipment and furniture during plan check is the safe way to save time.

When should I sign the lease?

After the space has been checked for exhaust, grease, utilities, parking and zoning. Ask the landlord for a rent-free period that covers permits and construction.

Let’s talk about your project!

Excited to begin your design journey? We're here to help you bring your vision to life and create something truly extraordinary together.